PROPOSED CAPITAL IMPROVEMENT PROJECT (2021)


PUblic meeting: Monday, April 5 at 6 p.m., LGI, in Person, Covid-19 social distancing and mask-wearing in effect

Virtual Information Meeting: April 8 at 7 p.m. Link will be posted at a later date

PROJECT VOTE ON TUESDAY, MAY 18 FROM 10 A.M. TO 8 P.M.; MS GYMNASIUM


SCOPE OF WORK

The proposed capital project focuses on asset preservation needs and health & safety improvements at the Wayland K-12 Campus, Cohocton Elementary Campus, and the bus garage. Key scope items at each location include the following:

WAYLAND K-12 CAMPUS ($9,559,000)

  • Emergency and secure lockdown system upgrades
  • Select exterior secure door replacements
  • Exterior and emergency lighting improvements 
  • Camera system upgrades
  • Instructional technology improvements
  • IT server and phone system upgrades
  • Ventilation and air handling system upgrades
  • Corridor flooring replacements
  • Elementary and Middle School kitchen renovations
  • Curriculum office renovations
  • Window glazing and sealant replacement
  • Partial roof replacements
  • Accessibility and safety improvements at bus loop
  • Replace/reconstruct deteriorated sidewalks
  • Exterior electronic message board replacement

COHOCTON CAMPUS ($1,165,000)

  • Fire alarm and emergency system upgrades
  • Exterior and emergency lighting improvements
  • Water softener, hot water heater, and piping replacement
  • Restroom exhaust system improvements
  • Kitchen and concession gas line replacement
  • Partial roof replacements (gymnasium, auditorium, and stage areas
  • Window glazing replacements
  • Replace/reconstruct deteriorated sidewalks and steps
  • Fencing and dugout protection improvements at baseball field

BUS GARAGE ($794,000)

  • Replace wash equipment
  • Replace overhead doors and operators
  • Replace fuel island canopy

Total Capital Project Cost: $11,518,000